Full launch includes beta and 11 public-launch items. Testing items earn half a point. Formal security sign-off, staffed support coverage and the public launch decision are production requirements. The name approval is complete, and the full device matrix runs during the employee beta wave.
18Done
11In progress
8To do
Beta next steps
Confirm tester access
Build 21 is assigned to Snoraire Internal, which has zero testers. The Android internal-test route worked on the Pixel. Use Internal TestFlight for eligible App Store Connect users or External TestFlight once Apple clears it. Employees without App Store Connect access need the External TestFlight route.
Shane
Record send or hold for the employee wave
Record send or hold by platform once the exact signed build is available to eligible testers and Marketing has approved the distribution list. The Digital Product Team sends approved invitations.
Digital Product Team, Marketing
Verify the builds during beta
Android build 14 passed its initial Pixel smoke test. Collect iPhone verification and remaining Android device evidence during the wave. Record each exact build and store route.
Shane, Jonas
Run the full overnight matrix during the employee wave
Record device-by-device results on the signed beta builds. Use the results and supported-device limits for the public production review.
Shane, Jonas, testers
Brand and identity 5 of 5 done
DoneBetaSetup
Choose the name and secure snoraire.com
Domain ownership is confirmed and the site runs on it.
Checked live 18 Nov
DoneBetaSetup
Create the new Apple and Google Play app records
Both exist under the new Snoraire app identity. The older Airese records are untouched.
ShaneRecorded 17 Nov
DoneBetaSetup
Set up signing and store upload access
Working for both platforms. Both builds below were signed and accepted.
ShaneRecorded 17 Nov
DoneBetaBuild
Include Snoraire branding in the beta builds
The new signed pair includes the final report wording. Check the installed experience on signed builds during beta.
Shane, JonasRecorded 19 Nov
DoneBetaApproval
Approve the Snoraire name for use
The project owner confirmed approval to use Snoraire on 20 November.
Publish privacy, terms and medical disclaimer pages
All three are live. The privacy policy includes the usage analytics section. An update saying analytics is off until the tester opts in, with no screen recording, is in review as website PR #5.
ShaneChecked live 18 Nov
DoneBetaBuild
Show beta download options
The site is in beta mode, with the Android internal test link and iPhone guidance.
ShaneChecked live 18 Nov
DoneBetaRelease
Publish the beta campaign handoff
The live beta buttons use the staging handoff. A synthetic test verified the campaign values. Verify the tagged campaign on installed apps during beta.
ShaneChecked live 19 Nov
App builds and testers 4 of 7 done
Beta Store Evidence has the store worksheets, reviewer instructions and dated receipts.
DoneBetaRelease
Upload the iPhone build, 0.1.14 (21)
Apple processed the signed replacement and lists it in Snoraire Internal and Snoraire External (Beta). External review and eligible installation are tracked below.
Play Console shows version code 14 active. A physical Pixel installed build 14 through Play internal testing.
ShanePlay Console readback 20 Nov
DoneBetaSetup
Match the app and website environments
Both signed beta builds point to the staging API used by the beta website.
Shane, ProductRecorded 19 Nov
DoneBetaBuild
Build and sign the staging pair
Both archives passed artifact inspection with their staging configuration and separate beta update channel.
Shane, JonasRecorded 19 Nov
In progressBetaBuild
Verify the signed replacement pair with opt-in analytics
Android smoke passed. A Pixel 7 Pro verified signup, analytics off by default and explicit opt-in, microphone recovery and short recording. Collect iPhone build 21, replay and overnight evidence during beta.
Google Play lists DPT and Testers. The Pixel installed build 14 through Play internal testing. Confirm store access for eligible testers, including the private iPhone invitation route when Apple clears External TestFlight.
ShaneStore console readback · 20 Nov
In progressBetaApproval
Make the selected build available in External TestFlight
Waiting for Review. App Store Connect shows build 21 in the external beta group. The build can be offered to external testers after Apple approves it. Record the eligible employee install during the beta.
Deployment and its authenticated smoke test passed.
ShaneRecorded 18 Nov
DoneBetaTesting
Test the campaign handoff on both platforms
Synthetic handoffs returned all four campaign values from staging.
ShaneRecorded 18 Nov
DoneBetaTesting
Write test leads to the Zoho sandbox
Synthetic Singapore and Malaysia leads were written and read back. The signed Android build has since delivered a callback to each regional sandbox.
ShaneRecorded 18 Nov
In progressBetaTesting
Run the full journey on a real phone
Both regional callbacks were confirmed in the signed Android app, returned HTTP 201 from staging and created matching Zoho sandbox leads. Singapore and Malaysia meet the beta care handoff criterion. The iPhone and tagged campaign checks remain open.
Shane, JonasPixel 7 Pro, AWS and Zoho readback · 20 Nov
In progressBetaTesting
Confirm the matching PostHog event
PostHog recorded the Pixel callback start and success with the same request reference. AWS and Zoho independently confirmed delivery. The server-side PostHog acceptance event still needs verification.
ShanePostHog, AWS and Zoho checked · 20 Nov
Beta tests and employee wave decision 2 of 5 done
DoneBetaSetup
Complete the four preparation gates
Build checks, access and staging readback passed for the candidate assessed on 8 Nov. The new builds still need the remaining gates.
ShaneLast assessed 8 Nov
In progressBetaTesting
Rehearse migration and recovery
CI migration and drift checks and a staging smoke test passed. Run a restore and rollback rehearsal using agreed recovery targets and record the outcome.
Shane, backup operatorCI and EAS-104/105 checked 19 Nov
In progressBetaTesting
Pass overnight testing on real phones
The device matrix and harness work have started. Run the full overnight matrix on builds 21 and 14 during the approved employee wave and retain results and failures for the production review.
Shane, Jonas, testersDevice matrix checked 19 Nov
DoneBetaTesting
Verify the Singapore and Malaysia care path
For beta, a matching lead visible in the regional Zoho CRM counts as care-team pickup. Signed Android build 14 produced a matching lead in each regional Zoho sandbox. Both employee-beta routing checks passed.
Product, care owners, ShaneSG and MY signed-device callback readback · 20 Nov · EAS-87
To doBetaOperations
Record the employee beta send-or-hold decision
Record send or hold by platform when the exact signed build is available to eligible testers and the distribution list is approved. DPT sends approved invitations. The full overnight matrix runs during the wave.
Agree the launch markets, platforms, owners and date in EAS-93. Mid-January is a working target. The tracker schedules go/no-go for 8–12 February.
Launch scope
Confirm Singapore and Malaysia, platforms and rollout order. Agree what February needs to deliver, including grant-acceptance evidence if applicable.
Product, Easmed management
Content calendar
Align pre-launch education, launch-day announcements and week-one follow-up by market, channel, owner and approval date. Publish install calls to action once the matching store links work.
Marketing
Operating process
Staff support and regional care queues. Rehearse a Zoho callback through human follow-up, incident escalation, rollback and pause communications. Name a primary and backup.
Shane, SG/MY care leads
Suggested features
Use employee beta evidence to rank a two-night comparison and improvements to the existing reminder. Commit a feature only after confirming the user need, capacity and release scope.
Product, Design
Bug fixes and device checks
Rank launch blockers across signup, overnight capture and recovery, reports and callbacks. Retest fixes on signed builds and record supported physical devices and any approved exceptions.
Jonas, Shane
Claims, privacy and security
Review the exact launch claims, consent, privacy and deletion flows. Obtain production security sign-off for the candidate and rehearse recovery before go/no-go.
Product, clinical and privacy reviewers, Shane
Public store release
Submit the production listings, screenshots, disclosures and signed builds to Apple App Store and Google Play. After approval and go/no-go, verify eligible installs in each launch market before website and campaign cutover.
Shane, Marketing
Launch monitoring
Check production attribution, signup, usable nights, reports, repeat nights and care handoff. Review the first 24 hours and seven days against agreed thresholds and record whether to continue, pause or roll back.
Product, Engineering, Marketing, care leads
Public launch checklist 0 of 11 done
In progressFull launchTesting
Confirm website analytics in Fathom
The live website bundle contains the Fathom configuration. A pageview receipt in the Marketing dashboard is still needed.
Shane, MarketingWebsite checked 19 Nov
In progressFull launchBuild
Add the public website access request form
The landing-page form is in draft PR #4. Confirm the public intake route and verify receipt before using it. The employee beta uses its own opt-in form.
ShanePR checked 19 Nov
In progressFull launchApproval
Approve public legal, support and deletion routes
Privacy, Terms and Contact are live. The /delete-account URL returned 404. Confirm the approved deletion method, support routing and legal versions.
Marketing, privacy, ProductWebsite and EAS-53 checked 19 Nov
To doFull launchSetup
Complete Google Play app setup
Finish the public app setup and verify it in Play Console. Google allows internal testing before this setup is complete.
ShanePlay guidance checked 19 Nov
To doFull launchRelease
Enable tracking on the production API
Staging deployment and smoke passed. Enable and verify the matching public attribution API before connecting the website.
ShaneStaging evidence checked 19 Nov
To doFull launchApproval
Approve store listings and disclosures
Draft copy exists. Verify the final screenshots, claims and privacy disclosures against the public candidate and record approval.
Marketing, privacy, ProductEAS-56 and EAS-75 checked 19 Nov
In progressFull launchApproval
Complete formal production security sign-off
Approve the exact production release line, including credentials, endpoints, least privilege, storage and logging, Terraform-state secret disposition and signed-device integrity.
Review the completed employee-wave device matrix, supported-device limits, recovery and rollback evidence, a monitored support route, named primary and backup, response targets, escalation, pause authority and communications, and regional care readiness. Record the release approver’s decision before public distribution.
The public iOS and Google Play listing checks returned 404. Confirm a live listing and eligible install in the approved launch markets.
Shane, release approverPublic links checked 19 Nov
To doFull launchRelease
Connect the website to production
The live website still uses the staging handoff. The public attribution API URL and Apple campaign token are blank in the served configuration.
ShaneWebsite configuration checked 19 Nov
To doFull launchRelease
Switch the website to public mode
The served website configuration is in beta mode. Enable public badges and remove the management review notes after public distribution checks pass.
ShaneWebsite configuration checked 19 Nov
“Checked live” means we tested the public site or store link on that date. “Apple readback” and “Expo readback” report each provider’s result. The unfinished items were rechecked on 19 November against the ticket tracker, live website, provider receipts and project evidence.
Beta invitations remain on hold. Android 0.1.10/26 was submitted to Play internal; iPhone 0.1.10/32 is valid and in internal TestFlight testing. Play track availability, approved tester access and physical installation still need verification.
Four preparation gates are complete. Store distribution is partial; security, migration and recovery, installed-candidate and overnight testing, SG/MY care and CRM, legal and support material, and final operations approval remain unfinished. Shane owns deployment and DevSecOps; Jonas supports application and build defects.
Checkpoint version: 2026-11-08-beta-release-preflight-v5. The release tracker above shows the 19 November builds and the remaining acceptance checks.
Decision notice
Current decisions · reconciled 11 November 2026
Password sign-in, the provisional formula, Night Notes and the bedtime reminder are approved product choices. Review decisions →
Decision details and evidence limits
Password sign-in, the provisional snore formula, Night Notes and the bedtime reminder are approved product choices, confirmed by Shane on 2 November. Jonas continues formula testing and tuning. Score categories, callback contracts, regional CRM details and legal/operational approval retain their open decisions and acceptance requirements.
Beta invitations remain on hold. The last release checkpoint, 8 November v5, records four preparation gates complete and seven unfinished gates. Android 0.1.10/26 and iPhone 0.1.10/32 were submitted; tester access, installed-device and overnight acceptance remain unverified.
Version 2026-11-11-decision-checkpoint-v1. The Notion decision timeline was updated and read back on 11 November; broader ticket acceptance synchronization is not claimed. Earlier conflicting text is historical. This is a reconciliation of saved evidence, not a fresh provider check or release approval.
The meeting decision supersedes the accountless product boundary in the 23 October audit below. Server-sync proof, legal/privacy, thresholds and Wednesday screen sign-off remain open. Reconcile the 11 November target with proposed mid-November feature lock; existing device gates remain unchanged. Read current decisions · 2026-10-26-signoff-v1. Earlier store/provider findings keep their original dates.
Three pieces of work can start today: the store package, the legal and data inventory, and the regional care handoff. None of them waits on open product decisions. Final store claims, privacy declarations and release sign-off come later, once the behaviour is agreed and a signed build exists.
We are not ready to release yet.
We have access to both store consoles, but the listings are incomplete and several product decisions and release concerns are still open. Completed evidence is kept below with its dates. The 11 November closed beta and the tentative mid-January public launch are still planning targets, not commitments.
27 October 2026 · 2026-10-27-meeting-v1
Launch planning and marketing alignment
The latest meeting adds detail to the launch plan. The product baseline remains email OTP. Formula, category, retention and release decisions still need approval. Earlier dated sections below are historical where this update identifies a conflict.
Wednesday 28 October: settle the product flow
Kedar will turn the full report wizard into a flowchart. Shane and Jonas will then identify what belongs in Phase 1 and later delivery. We need to agree widgets, the score formula, Ordinary/Unusual/Repeated Patterns, CTA triggers and wording, deletion and callback confirmation. Night comparisons and pause-count work remain deferred.
Thursday 29 October: agree the regional care handoff
The recorded direction is direct submission to Zoho by API, with form fields used as reference. We need to reconcile Singapore SCC pickup with the earlier SG CS route, confirm Malaysia CCC pickup, and agree the Singapore payment and booking sequence. Exact endpoints, permitted fields, staffing, fallback and response time remain open. Neither 24 hours nor three days is approved.
Shane, Jonas and Daniel coordinate the handoff discussion. Jonas is assigned to coordinate Malaysia access with Wei Jian. Access, destination receipt and human response each need evidence. Symptoms and sleep data mentioned in the notes are not an approved CRM payload.
Marketing and distribution
Daniel leads the recorded marketing track. Daniel and Maha will consolidate feedback for Kedar: mobile sign-up above the fold, shorter landing-page copy, drop-off analytics and store copy/design. Daniel will organize the proposed weekly TAS marketing execution meeting. Landing-page internal testing is targeted for the week of 2 November; completion has not been verified.
Product-side UTM attribution is assigned to Shane in the summary. We need to confirm the implementation owner against the PM-only role agreement. Paid channels and KOC content were discussed; no spend approval is recorded.
Dates and scope to confirm
Mid-November private/internal beta, December teasers and January/February public launch are planning direction. Reconcile the 11 November invitation target with the proposed mid-November feature lock.
The summary calls 50–100 users a minimum. Confirm the first batch and maximum against the earlier cohort range. Beta includes real Zoho care pickup, alongside app and algorithm checks.
Email OTP remains baseline. December/January SMS wording does not expressly replace the January deferral.
Local-audio/remote-analysis wording describes intent. Confirm actual processing transfers, retention, deletion and any separate research path before changing privacy notices.
Source: 27 October Granola meeting notes. The connector returned an AI-generated summary; full transcript access is unavailable. These notes establish no new clinical, legal, device or release acceptance. Screenshot requirements, regional clinical pathways and the broad IMDA deadline window require separate verification.
The Phase 1 PRD decision map (23 October) ties each open rule to its screens, tickets and evidence. Launch concerns C01–C19 below remain the shared release list.
Start now
These are suggested next steps. They do not create new assignments or deadlines; owners and dates stay as they are.
Work
Useful output now
What needs agreement
Store package Maha · existing end-of-October target
Draft the store copy, icon/feature-graphic brief and screenshot storyboard using the current UI and synthetic data.
Final score/claims, regional availability, support identity and candidate UI before approving screenshots or publishing copy.
Work through C01–C19 below and the wider release workstreams. Record each agreed rule, approver and impact on Kedar's screens and copy.
Start with score/report rules, data identity, legal acceptance and retention. Technical proposals need the relevant product, clinical or legal approval.
Privacy and legal preparation Product + Engineering + legal/privacy approver
Inventory the data, purpose, destinations, identifiers, retention and deletion for production, staging, research and analytics. Prepare document/declaration drafts from that inventory.
Confirm the controlling entity and approver. Finalise accessible documents, consent versions and audit evidence before collection or store declarations.
SG/MY care and support Existing regional Sales/CCC, IT and Marketing owners
Collect the approved Zoho form, regional contacts/store list, support inbox owner and campaign-link taxonomy. Draft the callback and escalation process.
Agree recipient, minimal payload, consent, response expectations and regional selection. Location detection and editable content infrastructure still need scope and estimates.
Release preparation Existing release and engineering owners
Complete review/integration, prepare signed candidates and schedule device evidence. Assemble review instructions and tester lists.
Do not submit or invite participants until the applicable legal, product, store and operational checks have evidence and named approval.
Verified store gaps
Read-only console inspection on 23 October, using Comet's f. profile. This supersedes the earlier access-blocked notes. No store settings were changed.
Apple App Store
Airese production · iOS 1.0 · Prepare for Submission
The Account Holder must accept the updated developer agreement before submission.
The inspected English (U.K.) iPhone screenshot slot contains 0 screenshots.
Description, keywords, support URL, copyright and reviewer contact/notes are blank.
No build is selected for this version.
Privacy Policy URL is unset; App Privacy declarations show Get Started.
Other device/localisation slots, pricing/countries, detailed policy answers and TestFlight processing were not fully audited. Uploaded binaries, completed setup tasks and physical acceptance are separate evidence.
Settle the data boundary before final copy
The V1 scope note records an accountless app with recordings/history on the phone, intended production database submissions and research uploads to R2. Server-held sensitive health data requires an agreed authentication, ownership and access-control design. We need to reconcile the exact payload, identity, access protection, acceptance audit and erasure design before implementing that boundary.
“Nothing leaves your phone” is not approved copy.
Production submissions, research uploads and analytics need their own accurate descriptions. Consumer login and backend authentication are different design choices; this page does not approve either a return to accounts or an authentication bypass.
The same-day compliance source review records placeholder legal text/consent versions and unresolved analytics notice/choice. Draft PR #37 is an implementation plan, not completed remediation or legal approval. The 120 MB/night estimate, fixed 10 pm reminder, eight-hour cap and battery observations below are supplied inputs, not fresh device measurements.
Shane coordinates PM and the decision pack; Jonas owns engineering under the recorded internal operating model. Maha’s launch assets and FAQ, and Shahira’s historical care-SOP assignment, need confirmed dates and acceptance receipts. The internal note reports Ervin as final product authority; formal delegation and separate operational, legal/privacy, release and pause authority still need confirmation.
Required record
Evidence to attach
Current limit
Candidate and test results
Signed build/configuration, supported device/OS, observed result and receipt for each required scenario, including unchanged EAS-26/27 overnight acceptance.
The new two-round plan is Not run. Meeting notes add no physical-device pass.
Unresolved defects
Candidate/device, severity and user/data impact, owner, fix/retest receipt or authorized exception with expiry.
A complete current-candidate defect inventory was not retrieved.
Release dependencies
Approved scope/rules, legal documents, store package, SG/MY receipt, phones, capacity and agreed sequence.
Reconcile the 11 November invitation target, proposed mid-November lock and earlier conditional 6 November go/no-go.
Historical prototype hours and API recovery do not establish current staffing or complete recovery acceptance.
Go/no-go
Named product/domain/release authorities, exact candidate and evidence reviewed, decision/date, conditions and invitation limit.
No go decision is recorded by this update.
Preparation can continue against the decision and test pack. These local additions are unpublished; the Notion checklist/timeline changes are pending access. Existing ticket properties and generated snapshots remain unchanged.
Shared release concerns
The product decisions are part of a wider release review across Product, Engineering, Design, Marketing, Legal/Privacy, IT and regional care. This workstream view overlaps the detailed decisions; it is not an additional issue count.
Workstream
Status
Current concern
Store package and submission
Open
Store access is available. Screenshots, copy, declarations, reviewer details and candidate selection remain incomplete in the inspected listings.
Legal documents and consent
Open
The source review records placeholder legal content and consent versions. Final documents, acceptance evidence and approval remain required.
Analytics notice and controls
Open
The source review did not establish a usable analytics choice/withdrawal control. Confirm the actual payloads and approved notice/data boundary.
Retention, withdrawal and erasure
Partial foundation
Local erasure and a research erasure queue exist. A complete retention policy and reliable end-to-end deletion evidence, including analytics and backups, remain open.
Claims and research participation
Open
Scoring/interpretation, permitted claims, research information, responsible contacts and the applicable approval evidence need agreement.
Signed candidates and device acceptance
Partial evidence
Host checks and an older staging Android UI smoke passed. Current signed Android/iOS recording, overnight resilience, supported-device coverage, replay and export evidence remain open.
Regional care and support
Open
Confirm SG/MY callback destination, CRM routing, permitted payload, support identity, FAQ, response ownership and escalation.
Commercial and launch scope
Open
Confirm free/paid scope, countries, languages, iPad support, beta recruitment and the treatment of the historical day-8 deletion proposal.
Release operations and approval
Open
Complete review/integration, candidate-specific acceptance, tester access, monitoring/triage and named go/no-go. The Apple Account Holder agreement action remains outstanding.
Evidence already completed
Completed checks remain visible with their dates and limits. They do not automatically close the related release workstream.
Evidence
Date
What was completed
Evidence limit
Store-console access
23 October
Company access to both stores verified in Comet f.; production app records identified.
Access is complete for this inspection; listing/submission readiness is still open.
Production infrastructure checks
19–20 October
Recorded API readiness/authentication smoke, image/configuration recovery and clean post-restore Terraform plan.
Historical infrastructure evidence, not acceptance of the latest mobile candidate or database-write rollback.
Storage and email probes
19 October
Synthetic production storage put/get/delete and cleanup passed; inbox delivery was confirmed by the operator.
Does not settle the final support identity, data retention or application recording/upload acceptance.
Release tooling and host validation
22–23 October record
The integrated stack records 12 repository checks, five builds, 26 JavaScript harness checks and three audio-tool checks passing.
Host validation and tooling preparation do not establish physical-device acceptance.
Physical staging UI smoke
22 October
An exact-source staging APK passed sign-in/signup/legal navigation on a Samsung SM-A356E running Android 16.
Older account-based staging source; no current local-first recording, export or physical iOS acceptance is implied.
Read the dated decision timeline for how the account, verification, Night Notes and callback discussions changed. The timeline is a notes-based draft, not an approval record.
Product and release decisions
These shared decisions remain open. Engineering confirms technical behavior and feasibility; Product and the relevant clinical, privacy, legal, Marketing and care owners approve their decisions. Design and copy depend on the agreed rules. These entries do not change ticket status or approved scope.
C01 · Snore Score formulation Open decision
Agree the formula, inputs, denominator, weighting and version. Record clinical/evidence limits; an implemented or researched formula does not establish product approval.
C02 · Metric bands Open decision
Define what low, moderate, often and severe mean for every applicable metric, including boundary values, units and user-facing wording.
C03 · Comparison across nights Open decision
Agree the reference average/window, minimum eligible nights, exclusions and comparable recording conditions. Specify when frequency and loudness comparisons can be shown, and the exact copy.
C04 · Night report categories Open decision
Define Ordinary, Unusual and Repeated Patterns, the conditions for each and whether the patterns are confirmed. Agree insufficient-evidence and fallback copy.
C05 · Unsuitable recordings Open decision
Agree thresholds that make a recording unsuitable for analysis and what the user sees. Keep invalid/insufficient evidence distinct from a reassuring low score.
C06 · Multiple sessions per day Open decision
Agree day/night grouping, timezone/cross-midnight treatment, aggregation versus separate sessions and their effects on trends and comparisons. Kedar needs the display rules.
C07 · Repeat sign-in and server data Open decision
Resolve the identity conflict above; define repeat sign-in/session behavior, ownership and access protection if sensitive health data is persisted remotely. Authentication and access protection must be specified in that case. Kedar and copywriters need the confirmed data boundary.
C08 · Recording prevention and reminders Open decision
Agree the minimum acceptable free storage and hard prevention/stop behavior, including copy and recovery. The supplied consideration is that charging state may be detected but battery level should not be assumed available; confirm this on supported platforms before promising a battery-level rule.
C09 · Recording retention and pruning Open decision
Agree how long original audio is kept, the pruning trigger/order and what reports remain after audio removal. The supplied estimate is approximately 120 MB per eight-hour night; this is a planning estimate, not a measured release budget. Kedar needs the pruned-night state.
C10 · Bedtime reminders Open decision
Decide whether reminders are customisable and specify time, timezone, opt-in and rescheduling behavior. The current reminder is reported as fixed at 10 pm; this observation has not been re-tested here.
C11 · Eight-hour stop and sleep chart Open decision
Resolve the reported eight-hour recording cap against charts that imply users can record more than eight hours or meet a longer “healthy” range. Distinguish recording duration from measured sleep; agree the cap, graph and copy together.
C12 · Terms, Privacy and acceptance audit Open decision
Approve both documents with PostHog and actual data flows included. Decide account-linked versus accountless acceptance in line with C07; define document versions, acceptance timestamps, audit evidence and reacceptance. Engineering needs the confirmed model before designing acceptance storage.
C13 · Research participation Open decision
Prepare separate research terms/consent for uploads, including externally referred participants. Agree recruitment eligibility, recipients, purpose, withdrawal and acceptance evidence before sending research builds outside the team.
C14 · Erasure Open decision
Agree local/server/research data deletion and retention obligations from the approved Terms and Privacy Policy, including what happens to retained reports, consent audit evidence and backups. Implementation follows the approved policy.
C15 · Callback payload and destination Open decision
Confirm what is sent to regional Sales/CCC, the approved Zoho form URL, consent and minimum necessary fields. Keep health data out of the handoff unless explicitly approved.
Agree the campaign links, parameter taxonomy, attribution rules and consent/data boundary across store/install/app/callback. Confirm the owners and evidence needed for the full journey.
C18 · Support identity Open decision
Choose the monitored support address and domain: Snoraire versus The Air Station. Confirm inbox owner, backup and where the address appears in-app, in legal documents and in store listings.
C19 · SG/MY contacts and store locations Open decision
Approve the contact/location inventory, regional selection rule and whether device location is actually required. Editable database-backed content is proposed that can be updated/synced without an app release; confirm editor ownership, freshness/fallback, privacy/permissions and engineering scope/time before commitment.
Then approve the release package
Record decisions with approvers, versions and affected screens/tickets.
Finalise legal documents, declarations, copy, screenshots and regional/support details against the candidate.
Attach the exact build, complete review information and tester setup, and retain signed-device evidence.
Obtain the named product, operational and release go/no-go before submission, invitations or public rollout.
This is a dated editorial launch review. The delivery tracker continues to use its established one-way Notion snapshot; this page does not update ticket counts, statuses or owners. Changes to approved requirements need explicit ticket/document reconciliation.
Local counterparts: airese-beta-decisions-2026-10-08.md and the production release preparation/handoff documents, shared 23 October version v5; store evidence remains the dated v3 inspection. No formula, threshold, legal position or launch commitment is approved here.