Airese (Beta)

How we will ship it

Team discussion, 22 September 2026

Today’s map

How we work

01 PRIORITISE

Pick the thing most likely to go wrong, and do it first.

02 BUILD

Build one small piece at a time, with one person responsible.

03 VERIFY

Prove it works — on real phones, with real people.

04 LEARN

Compare what happened with what we expected.

05 ADAPT

Change the plan, and flag early when something is stuck.

How a change reaches a phone

PlanAgree what we’re fixingand how we’ll know BuildMake the change andhave someone check it Put togetherCombine everyone’s workand run the checks ReleaseSend the approved appto testers’ phones WatchWatch for crashes andsupport requests LearnUse what we learnto change the plan

At Easmed, this loop takes Airese from an agreed risk, through a finished app, to the approved phones. What we learn from the first testers then shapes the next decision.

Hover or focus a stage to explore it.

Adapted from Atlassian, DevOps with Atlassian, 2017, page 6.

Airese in the patient journey

One timeline from Snoraire discovery through treatment and continuing care The patient journey begins with a sleep concern and Airese discovery. The proposed beta journey runs in purple through consent, a supported night, the agreed result and a callback from a person. Grey stages then continue to doctor and sleep testing, diagnosis, CPAP trial, purchase or adjustment, and ongoing care. Grey branches above the app stages show things that could come later. WHERE AIRESE HELPS WIDER CLINICAL JOURNEY COULD COME LATER Education anddiscovery Device and healthintegrations Night trendsand analytics Sleep qualityand readiness Follow-uptools Sleepconcern DiscoverAirese Join andconsent Supportednight Agreedresult Humancallback Doctor andsleep test Clinicaldiagnosis CPAPtrial Purchaseor adjust Continuingcare Snoring or fatigue Entry channel Privacy + eligibility Overnight capture Clear, agreed copy Named support owner Clinical assessment Report review Fit + education Benefit decision Therapy support THE BETA JOURNEY · PROVED ON APPROVED PHONES HANDLED BY CLINICAL TEAMS, NOT THE APP

Sources: supplied journey-map.html and Easmed’s patient-journey map, 25 August 2026. Purple path: proposed 11 November beta.

Beta decision

What’s in the beta

Agree what the overnight journey includes and what can wait. If a tester asks for help after their result, who takes that call?

Who it’s for, and what we say

Agree what we can say the score means, who can join in Malaysia and Singapore, and how they hear about it.

Which phones we support

Approve the priority iPhone and Samsung models for Malaysia and Singapore. Recording and battery results differ by phone.

Who decides

Name who signs off on clinical, privacy and release, and who can stop the beta if the evidence doesn’t hold.

Release gate: before the first invitation — a sleep-study check on the score, overnight tests on the approved phones, the finished app ready to send, privacy and support in place, and a written go/no-go.

Decision owners: Gary and Ervin decide scope and claims today, and record the 10 Nov go/no-go. No invitation goes out before that is recorded. The cohort opens 11 Nov only if the gate passes; 18 Nov is the contingency and needs replanning.

Source: 21 September engineering discussion and Easmed Notion, 22 Sep readiness, mobile launch gate and 11 Nov beta views.

Planning principles

Area · what we’d change
Time from start to launch = 100%
0%25%50%75%100%
What we get
01 · What we buildBuild less
Less to build and test
A complete beta journey
02 · The score and recordingProtect Jonas
Less interruption
More time on the score
03 · Building and releasingSpeed up builds
Less waiting for builds
Releases we can repeat
04 · MeasuringTrack metrics
Less rework
We can see what’s working
05 · Getting startedReduce friction
Less support time
More successful first nights
06 · Finding testersUse marketing
Less waiting for testers
Better-matched testers

Shaded portions are time we could remove. Positions and widths are illustrative, not estimates. Hover or focus a bar to see what to do.

Draft snoring score

What goes into it

50%How loudThe loudest snores
40%How longTime spent snoring while asleep
10%How oftenNumber of snores

50% loudness + 40% time + 10% frequency

Breathing pauses: shown separately. This score does not tell us how severe sleep apnea is.

Source: Airese score-concepts.md (9 September 2026) and draft snore/breathing score architecture. Product and clinical decision remains open in EAS-2.

What “ready for beta” means

01 Agreed scope

Agree the beta journey, who it’s for, and what we can say the score means — including its limits.

As a beta owner, I can explain who this release serves and what the score means.

02 Tested overnight journey

Prove consent, overnight recording, recovery after problems, and results on the agreed phones.

As a tester, I can complete a supported night and understand my result.

03 Getting the app out

We can produce the finished app reliably, send it to testers, delete data on request, support people, and undo a release if needed.

As a release owner, I can send the approved app and undo it safely.

04 What we can measure

We can see how far testers get, and when recordings, the app or the analysis fail.

As a product or support owner, I can see where testers stall and when the system needs help.

05 Beta decision

Record the go/no-go against the phone tests, score limits, release readiness and any exceptions. Review the first 24 hours.

As a decision owner, I can open, pause or roll back the cohort based on evidence.

Source: Easmed Notion, Product & Engineering Tickets, 22 Sep readiness, mobile launch gate and 11 Nov beta views, read 21 September 2026.

Launch plan

Launch objective: a tester completes an overnight recording and gets the agreed result, with support available and the ability to pause. The 11 November invite-only beta is conditional; what ships in February depends on what we learn.

September
October
November
December to February
Launch objective
22 Sep
29 Sep
6 Oct
13 Oct
20 Oct
27 Oct
3 Nov
10 Nov
17 Nov
27 Nov
Dec–Jan
28 Feb
What we build and claim
22 Sep decisions
Recording and analysis
Sleep studies, recording, analysis, battery
Design and supported phones
Design handover, safety, accessibility, phone testing
Building and releasing
Set up, back up, sign, first release build
iPhone · Apple TestFlight
Sign + prepare · 1–2d + 2–3d
Review · 5d
Prove · 1–2d
Mid-Dec public submission target
Android · Google Play testing
Sign + prepare · 1–2d + 2–3d
Play · 7d
Prove · 1–2d
Privacy and data rights
Consent, retention, deletion
Testers and sign-ups
By 2 Oct · playbook
23–30 Oct · rehearsal
11 Nov · invite waves
Monitoring and support
Monitoring, alerts, support, launch controls
Evidence and decision
5–6 Nov proof · 10 Nov decision · 11 Nov beta
Post-beta learning
First 24h → 27 Nov · watch and decide
Approved work → Feb gate

Sources: Easmed Notion cohort plan, beta gate, EAS-47, EAS-56, EAS-63, EAS-65, EAS-69, EAS-93 and EAS-107–109; Apple TestFlight and Google Play. Dates and review times are planning allowances.

Which phones we test on

Phones to approve

iPhone 15 PlusOur existing iPhone reference
iPhone 12Older phone and battery behaviour · need to borrow one
Galaxy S24Samsung flagship · use the team's exact S-series model
Galaxy A35 SM-A356EOur existing older Samsung — the risky one
Google PixelWei Jian's phone · Android control outside Samsung

The same check on every phone

FreezeThe app version, the phone’s software, microphone settings, score version, and where the phone sits.

ComparePlay the same recording to every phone and check the scores match.

Run real nightsCharging, app open, screen off and face down, allowed to record in the background.

Decide phone by phoneKeep the nights that fail. Report how many finished, battery use, crashes and result quality.

Sources: Easmed Product Wiki, EAS-9 and EAS-48; updated 24 September after the device-matrix discussion. Record the exact Galaxy S-series and Pixel models before testing.

Risks and how we handle them

Score claim outruns evidence

Mitigate: don’t show the number until the sleep-study check, repeat testing and the clinical wording are signed off.

Overnight recording fails

Mitigate: test the finished app on every approved phone; keep the nights that fail and judge by completion, battery and audio quality.

The app reaches phones late

Mitigate: make the release process reliable, lock the settings, and rehearse Apple and Google installs early.

Apple or Google review takes longer

Mitigate: prepare store information and account access early; leave room for review and possible rejection before invitation dates.

Specialist time gets spread thin

Mitigate: protect Jonas’s time for the score, and make workload, blockers and decisions visible every week.

Tester evidence is weak

Mitigate: check phone fit, invite in waves, track where people drop off, and assign a support owner for first-night problems.

Basis: Easmed Notion beta gates, score decision, device matrix, launch evidence and cohort plan, reviewed 21 September 2026. Mitigations are proposals for 22 September agreement.